The projected started on April 27/2017 at 8 project site namely Tendaho, Kesem, Metehara, Wonji, Arjo, Fincha, OmoKuraz and Omo 2. The project activities include node installation, fiber root installation, and data centre organizing and server and switch configuration. Currently 98% of the project activity are completed and on the way delivering the site to the corporation.
Around 1698 node, 44 power & UPS, 17,987 mt. fiber cable pulling, 1196 fiber optics installation and termination and other activities conducted.